A two-year, $9.3 million project is set to secure the renewable energy future of Alice Springs. The Alice Springs Future Grid Project will focus on addressing barriers to further renewable energy penetration in the local electricity network.

Currently, Alice Springs has approximately 10% renewable energy generation and faces a unique challenge in overcoming system strength issues to serve approximately 30,000 people, with communities stretching as far as 130 km from the town.

With $2.17 million support from the Australian Government via the Australian Renewable Energy Agency (ARENA), the project will address technical, regulatory, social and economic challenges with energy transition in the town’s isolated grid through a series of subprojects including:

  • a large-scale battery system;
  • a residential battery trial for up to 50 customers, with batteries aggregated and controlled to provide voltage support to the network;
  • tariff reforms to investigate the commercial and other incentives required to encourage a change in consumer behaviour to facilitate higher uptake of household batteries with rooftop solar;
  • a roadmap for how the Alice Springs electricity grid could operate with 50% renewables by 2030.
     

The project will be led by the Intyalheme Centre for Future Energy, a flagship project of Desert Knowledge Australia (DKA), supported by the Northern Territory Government. ARENA’s funding is provided through the Desert Knowledge Research Institute and will complement the $3.19 million in funding DKA received as part of the Australian Government’s $50 million Regional and Remote Communities Microgrid Fund.

ARENA CEO Darren Miller said the project would provide much-needed support to help the town overcome challenges and transition towards renewable energy solutions.

“This project will lead to the development of a tangible roadmap for increased renewable energy adoption in Alice Springs. The lessons learned will also contribute to the broader Northern Territory and other remote Australian microgrid communities,” he said.

Tristan Simons, General Manager of the Intyalheme Centre for Future Energy, said, “Alice Springs Future Grid takes a unique approach to a multifaceted challenge, in a rapidly changing environment.

“Alice Springs is ‘small enough to manage but big enough to matter’, and we are confident the project will not only help secure a clean and reliable energy future for the town, but the knowledge generated will have a positive flow-on effect, well beyond the other isolated electricity networks in the Northern Territory.”

Alice Springs Future Grid is governed by a steering committee including CSIRO, Ekistica, Power and Water Corporation and Territory Generation, along with representatives from ARENA and the Northern Territory Government.

Related News

Untapped solar could achieve billions in savings

UNSW research has found that people living in apartments, social housing and private rental...

NSW South Coast gains its first community battery

The Shell Cove battery is one of 54 batteries currently being rolled out across Endeavour's...

The sustainability sector's thoughts on a 'future made in Australia'

Hear thoughts from leaders in heavy manufacturing and climate tech, regional areas and cities as...


  • All content Copyright © 2024 Westwick-Farrow Pty Ltd